TRINITY RIVER MAIN STEM PUMP STATION & PIPELINE

CMAR
Garney Construction

 

Originally conceived as a temporary pump station as a drought contingency measure, significant rains in 2012 caused the North Texas Municipal Water District to re-envision the project as a permanent pump station. Because of the size of the project and remote project location, NTMWD chose a CMAR for management and execution.

Trinity River enhanced.20221216154357256

Download this project spotlight to learn more:

  • How the CMAR delivery method benefited this project
  • Notable accomplishments during adverse conditions
  • How multiple bid packages and equipment purchase packages helped this project stay on schedule